19 July 2019

Queens Place Construction Update-June 2019

Works are continuing at Queens Place with Multiplex progressing on many fronts:

– Basement services and preparation for fit-out works.

– Podium structure

– Lift cores – currently at level 8.

In the last month several podium levels have been completed and feature fins have been installed. The retail, office and supermarket tenancies are taking shape as are the apartment amenity areas – gym, games rooms and private dining areas.

There are over 120 people on site each day. Works off site include façade panels, lifts and services equipment. In the coming months we’ll see the first facade panels installed and level 5 pool areas take shape.

13 June 2019

Queens Place Construction Update-May 2019

The podium levels at Queens Place continue to take shape with Multiplex currently constructing the level 2 slab.

The two lift cores are at level 6, well above street level and visible from the nearby streets.

Manpower continues to increase with structural and services trades being the majority of the 130 people on site. The apartment lobbies, retail area and office tenancies are taking shape as is the central atrium space.

In the coming month we’ll see the podium fins installed and the preparation for the facade panels.

16 May 2019

Queens Place Construction Update-April 2019

Works continue at a rapid rate at Queens Place. Multiplex continue with progress on many work fronts including the basement, podium and lift cores.

In the last month the basement structure has been completed and the ground floor slab has taken shape. We can now see the outline of the residential lobbies, supermarket and retail shops and carpark entry.

The two lift cores are at level 2 and easily visible from the street.

There are over 120 people on site each day. working on Queens Place. Works off site include façade panels, lifts and services equipment.

18 April 2019

Queens Place Construction Update-March 2019

Site works at Queens Place continue to progress on program. Multiplex have reached street level and the basement structural works are complete.

Construction trades continue to work on the basement services and concrete structure.

Two tower cranes are installing precast and the key areas of the ground floor and level 1 structure.

The lift cores are at level 2 and with over one hundred construction workers on site Queens Place is starting to take shape.

Offsite subcontractors have completed prototype kitchens, façade panels, lifts and escalators for the project. All will be installed in the near future.

13 March 2019

Queens Place Construction Update-Feburary 2019

Another busy month on site with Multiplex continuing with works on the basement levels. We have now completed basement 2 to 6 and have commenced the supermarket level at basement 1.

The lift cores are above street level and continue to rise each week.

Multiplex have approximately 80 people on site each day completing the structure, services and other construction works.

07 February 2019

Queens Place Construction Update-December 2018 and January 2019

Multiplex continue with works at Queens Place.

In the last month columns and slabs have been completed up to basement 4.

Signage has been installed to the lift cores, the cores are now almost at street level.

There are approximately 80 people on site working on Queens Place and Multiplex are currently around 2 weeks ahead of their program.